乐昌峡水利枢纽营区拦水坝及排洪设施施工技术综述

Construction Technique of Dam and Drainage Facilities in Lechangxia Hydro-Junction Project Camp
下载PDF
导出
摘要 乐昌峡水利枢纽营区位于坝址左岸上游1 km处,该场地为拦河坝坝肩边坡开挖弃渣填筑而成,整体稳定性较差,排洪设施布置及施工应充分考虑地质、水文、交通等条件,通过枢纽营区修建拦水坝、排洪沟及排水管网系统等永久性排水设施,将北溪冲沟水和地表水流导向武江河,解决了大面积填筑场地水土保持及稳定问题。 The camp of Lechangxia Hydro-junction is located 1km upstream of the left bank of the site,but the site is made to block the slope of the dam on the side of the dam,and the whole stability is poor.The layout and construction of the drainage facilities shall be fully considered in the conditions of geology,hydrology and transportation.In this paper,the permanent drainage facilities for the construction of dam,drainage and drainage network system are discussed in this paper.It is very good to solve the problem of soil and water conservation and stability in large area.
作者 林志鸿 LIN Zhihong(Management Office of Lechangxia Hydro-junction Project,Lechang 512200,China)
出处 《广东水利水电》 2018年第4期47-51,59,共6页 Guangdong Water Resources and Hydropower
关键词 乐昌峡 水利工程 拦水坝 排洪设施 施工 Lechangxia hydro-junction project hydraulic engineering dam drainage facilities construction
  • 相关文献

参考文献1

二级参考文献2

  • 1姚礼敏,刘力捷.广东省乐昌峡水利枢纽工程初步设计报告[R].广州:广东省水利电力规划勘测设计研究院,2009.
  • 2SL 303-2004,水利水电工程施工组织设计规范[S].