摘要 本文结合南京G205国道下穿宁启铁路顶进涵施工,针对既有多股线路大跨度顶进涵施工难题,提出了一种新型的现浇门桩结构,设计了多股线路大跨度顶进线路加固施工方案,并运用数值模拟的方法模拟门桩在加载状态下的力学响应。该门桩是由两根现浇人工挖孔桩和顶部系梁构成的钢筋混凝土整体结构。数值模拟的结果显示,门桩结构能够有效地分摊荷载,显示优越的承载能力。本文总结现浇门桩结构特点、实现步骤以及原理,以实现该技术更进一步的推广与应用。 The gate-pile structure is a kind of structure like the doors’.In this paper,a new gate-pile is presented and a multi-strand line large span roof into the line reinforcement construction scheme is design to solve the problem of the large span multi-strand lines culvert jacking construction based on the culvert jacking construction wearing under Ning-Qi railway.And the structure is simulated by the numerical simulation method to test its mechanical response under loading.The result shows that the load was perfectly shared by the structure,showing the structure’s perfect ability of bearing force.This paper summarizes the characteristics,implementation steps,as well as the principle of the gate-pile structure,in order to realize the further promotion and application of the technology.
作者 吴文华
出处 《科技创新导报》 2018年第8期73-76,78,共5页 Science and Technology Innovation Herald
关键词 既有线 近接施工 门桩结构 桥涵顶进 大跨度 线路加固 Existing railway line Approaching excavation Gate-pile structure Culvert jacking construction Large span Stabilization of the roadway
  • 相关文献

参考文献11

二级参考文献25

  • 1杨广林.D型便梁加固线路顶进箱桥施工技术[J].内蒙古科技与经济,2006(06X):141-142. 被引量:13
  • 2刘成宇,华祖火昆.土力学.北京:中国铁道出版社,2005.
  • 3中铁宝桥.D型施工便梁使用说明书,2004.
  • 4铁道部第三工程局.桥涵[M].北京:中国铁道出版社,1994.
  • 5铁道部第三勘测设计院.铁路桥涵设计基本规范[M].北京:中国铁道出版社,2005.
  • 6范立础.桥梁工程[M].北京:人民交通出版社,2003..
  • 7杨文渊,徐彝.桥涵工程师手册[M].北京:人民交通出版社,1997.
  • 8陈旺.隧道下穿既有线采用D型施工便梁进行线路加固施工技术[J].城市建设理论研究:电子版,2013(10).
  • 9王海洋.D型施工便粱架设过程关键点控制浅析[J].城市建设理论研究:电子版,2012(11).
  • 10冯生华,张孚衍.城市地道桥项入法施工[M].北京:中国建筑工业出版社.1982.

共引文献32

同被引文献9

引证文献4

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部