期刊文献+

核电厂首次主回路水压试验最高试验压力选择

Selection of the highest test pressure for the first primary loop pressure test of nuclear power plants
下载PDF
导出
摘要 核电厂在建设期间,均要对封闭主回路执行一次超压水压试验,以检查主回路及相关辅助系统的安装质量。本文主要通过对不同设计规范对于核电厂首次主回路水压试验最高试验压力的不同规定,分析出其差异性,希望为核电厂主回路水压试验最高压力选择提供参考。 During the construction of the nuclear power plant,an overpressure hydrostatic test is carried out on the closed main circuit to check the installation quality of the main circuit and related auxiliary systems.In this paper,the difference of the maximum test pressure for the first main circuit hydraulic test of the nuclear power plant is analyzed by different specifications,and it is hoped to provide a reference for the selection of the maximum pressure of the water pressure test in the main circuit of the nuclear power plant.
作者 张翔 ZHANG Xiang(East China Branch of China Nuclear Power Engineering Co.,LTD.,Jiaxing Zhejiang 314300,China)
出处 《科技视界》 2018年第33期165-166,168,共3页 Science & Technology Vision
关键词 主回路水压试验 最高试验压力 保压时间 Main circuit hydraulic test Highest test pressure Dwell time
  • 相关文献

参考文献1

共引文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部