某水厂取水口迁建工程设计案例 被引量:5

Design case for relocation project of water intake of a water treatment plant
下载PDF
导出
摘要 近年来,随着水源地保护力度不断加大,出现了一些需要搬迁的取水口。为保证取水口迁建后取水能力不变,需以现状系统的最低取水水位、水头损失和起泵吸水井最大水位降落差作为设计的约束条件,通过优化取水管线路,扩大取水管管径等方式,对冲由于迁建导致的取水距离增加。以某100万m^3/d取水口迁建工程为例,介绍了相关的设计步骤和内容。 In recent years,with the increasing protection of water sources,there have been some water intakes that need to be relocated.In order to ensure that the capacity of the water intake is unchanged after the relocation,it is necessary to use the minimum water level,head loss and maximum water level drop of the pumping well as the design constraints,by optimizing the water intake line,expanding the way of taking water pipes,etc,solve the increase in water intake distance due to relocation.This paper takes a one million m3/d water intake relocation project as an example and introduces the relevant design steps and contents.
作者 肖敏杰 高志强 马永恒 Xiao Minjie;Gao Zhiqiang;Ma Yongheng(Shanghai Municipal Engineering Design Institute (Group)Co.,Ltd.,Shanghai 200092,China;Shanghai Water Design & Engineering Co.,Ltd.,Shanghai 200092,China)
出处 《给水排水》 CSCD 北大核心 2019年第4期24-29,共6页 Water & Wastewater Engineering
关键词 水源地保护 取水口迁建 取水管延长 水头损失 水位降落 Water source protection Water intake relocation Pipe extension Head loss Water level landing
  • 相关文献

参考文献1

同被引文献19

引证文献5

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部