摘要
管板桩沉桩施工技术能适应较复杂的地质情况,尤其适用于有成本限制和工期较短的深水化码头工程建设。以安哥拉渔港成品油库扩建项目码头与疏浚工程为例,研究了管板桩沉桩施工技术在工程中的应用。
The construction technology of piling with tubular plies and sheet piles can adapt to more complicated geological conditions,especially for the construction of deep dock with cost limitation and short construction period.Taking the dock and dredging project of fishing port product oil depot expansion project in Angola for example,the application of piling with tubular plies and sheet piles technology in this project was introduced.
作者
曹鹏
李明涛
麻涛
何永兴
Peng Cao;Mingtao Li;Tao Ma;Yongxing He(China Petroleum Pipeline Engineering Co.Ltd.International,Langfang Hebei)
出处
《石油天然气学报》
CAS
2019年第2期41-44,共4页
Journal of Oil and Gas Technology
关键词
管板桩沉桩施工技术
深水化码头
码头工程建设
疏浚工程
The Construction Technology of Piling with Tubular Plies and Sheet Piles
Deepwater Wharf
Wharf Engineering Construction
Dredging Engineering