摘要
为深入研究隧道穿越不良地质段的施工控制技术,以黎家湾隧道为工程实例,全面总结分析黎家湾隧道的工程地质情况,提出了采用超前小导管注浆、注浆堵水加固、台阶分部开挖法等施工控制技术,并通过数值模拟计算对其控制效果进行评价。研究结果表明采用上述施工控制措施后,隧道围岩及支护结构变形得到了有效控制,研究成果对类似工程有供借鉴意义。
In order to study the construction control technology of tunnel crossing bad geological section in depth, the Lijiawan Tunnel is taken as an engineering example to comprehensively summarize the engineering geological conditions of the Lijiawan Tunnel, the construction control technologies are used, such as the grouting of the leading small pipe, the reinforcement of water plugging, the method of excavation by steps and so on. Also, the control effect is evaluated by numerical simulation. The research results show that after the above construction control measures, the deformation of the surrounding rock and supporting structure of the tunnel have been effectively controlled, and the research results can be used for reference for similar projects.
作者
程佳
战启芳
刘训臣
CHENG Jia;ZHAN Qi-fang;LIU Xun-chen(Shijiazhuang institute of railway technology Shijiazhuang Hebei 050041 China)
出处
《石家庄铁路职业技术学院学报》
2019年第2期30-34,共5页
Journal of Shijiazhuang Institute of Railway Technology
基金
河北省高等学科科学技术研究重点项目,长大高风险铁路隧道施工关键技术研究与实施,项目编号:ZD201517旋扩珠盘桩承载性状研究,项目编号:ZD2015115
关键词
黎家湾隧道
不良地质段
施工方案
有限元计算
LiJiaWan tunnel
bad geological section
construction plan
finite element calculatio