顶管施工引起地表竖向变形分析 被引量:6

Analysis of Soil Vertical Deformation Induced by Pipe Jacking Construction
下载PDF
导出
摘要 顶管法在各个城市的地下管线施工中广泛运用,尤其在已建道路下的管线施工中具有优势。顶管穿越路基施工引起管道周围土体变形易对路面造成变形破坏。结合实际工程,分析计算顶管施工正面附加推力、设备与周围土体的摩擦力对地表垂直变形的影响,结合土体损失引起的竖向变形,计算顶管施工引起总的周边地表竖向变形。计算结果与实际监测结果吻合,顶管施工引起周边地表竖向变形呈现前方隆起后方沉降的变化规律。 Pipe jacking has been widely used in the underground pipeline construction, especially in the pipeline construction of road engineering. When pipeline passing through the roadbed, the deformation of soil may be so large that destroy the road surface. According to a certain practical engineering, this paper calculated the soil vertical deformation induced by bulkhead additive thrust and the force of friction between jacking device and soil. Combining the formula of ground deformation induced by ground loss, the formula of total soil vertical deformation induced by pipe jacking construction is obtained. The calculated results agrees well with the actual monitoring results, due to pipe jacking construction, the frontal soil of excavation face heave and the rear soil subside.
作者 苏越 张敏 李更召 张成君 邢卫民 SU Yue;ZHANG Min;LI Gengzhao;ZHANG Chengjun;XING Weimin(Tianjin Institute of Geotechnical Investigation and Surveying,Tianjin 300191,China)
机构地区 天津市勘察院
出处 《水利与建筑工程学报》 2019年第3期208-211,230,共5页 Journal of Water Resources and Architectural Engineering
关键词 顶管 地表竖向变形 正面附加推力 摩擦力 土体损失 pipe jacking soil vertical deformation bulkhead additive thrust force of friction ground loss
  • 相关文献

参考文献11

二级参考文献73

共引文献52

同被引文献45

引证文献6

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部