GIL运输专用机具作为苏通GIL综合管廊工程GIL设备安装工程的关键施工装备,其行走机构的设计型式将直接决定着整机研制的技术路线。结合苏通GIL综合管廊工程的工程特点,通过对轨道式(双轨)、轮胎式(无轨)、轮胎式(单轨)3种技术方案的深入研究和全面比选,给出了3种技术方案的优缺点,得出了选取轨道式(双轨)技术方案作为GIL运输专用机具的结论。
The special transport equipment for GIL transportation is used as the key construction equipment in the GIL equipment installation of the Sutong GIL comprehensive pipe corridor project. Its design directly determines the technical route of the whole machine. In this paper, according to the engineering characteristics of Sutong GIL comprehensive pipe corridor project and through in-depth study and comprehensive comparison of three technical schemes of track type (double track), tyre type (trackless) and tire type (monorail), their advantages and disadvantages are given out, and it comes to the conclusion that the track type (double track) technical scheme can be selected for the special equipment for GIL transportation.
作者
韩先才
熊织明
高亚平
范江波
宋帅
毕涛
王丹
米勇
HAN Xiancai;XIONG Zhiming;GAO Yaping;FAN Jiangbo;SONG Shuai;BI Tao;WANG Dan;MI Yong(State Grid Co., Ltd., Beijing 100031, China;Engineering management department, State Grid Co., Ltd., Beijing 100052, China;Jiangsu Diversion Co., Ltd., Naning 210037, China;Taiyuan Heavy Industry Co., Ltd., Taiyuan 030024, China)
出处
《机械制造与自动化》
2019年第4期176-179,共4页
Machine Building & Automation