综采工作面巷道护巷煤柱留设尺寸研究 被引量:1

Study on the Size of Coal Pillar in Protective Roadway of Fully-mechanized Mining Face
下载PDF
导出
摘要 以西河煤矿3号煤层工作面护巷煤柱留设为背景,通过建立力学模型分析了煤柱的整体受力状态并计算出了煤柱的合理尺寸,运用数值模拟分析了工作面回采过程中煤柱受力情况及围岩破坏情况,得出煤柱留设的合理宽度为15 m。并在现场得到成功的应用。为类似条件下工作面顺槽煤柱留设提供科学依据。 In the condition of no.3 coal seam coal mine working face this chain pillars as the background,by establishing the mechanical model overall stress state of coal pillar are analyzed and calculated the reasonable dimension of coal pillar,in the process of mining face were analyzed by using numerical simulation stress distribution and damage of surrounding rock and coal pillar that leave a set of reasonable coal pillar width is 15 m and get success in the field of application for the similar working face under the condition of the groove design,to provide scientific basis for the coal pillar.
作者 刘伟 LIU Wei(Emergency Management Bureau of Yangcheng County, Jincheng City,Yangcheng 048100, China)
出处 《煤》 2020年第3期8-10,共3页 Coal
基金 内蒙古自治区自然科学基金资助项目(2018LH05009)
关键词 护巷煤柱 数值模拟 应力 roadway pillar numerical simulation stress
  • 相关文献

二级参考文献34

共引文献16

同被引文献11

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部