长距离岩石顶管施工关键技术 被引量:7

Key Techniques for the Construction of Jacking Pipes Through a Long-Distance Rocky Stratum
下载PDF
导出
摘要 国内目前岩石地层顶管应用极少,千米以上的超长距离岩石顶管没有相关案例。依托重庆市观景口水利枢纽工程,重点对长距离岩石顶管机的设备选型、润滑减阻、长距离导向与纠偏、中继间优化布置等施工关键技术进行了系统研究,并在施工中取得了成功应用,具有较高的推广应用价值。 Right at present,the application of jacking pipes through rocky strata is very rare in China,and there are even no related cases of jacking pipes through rocky strata over the distance of one kilometer reported.With the Guanjingkou Water Conservancy Hub Project in Chongqing as the technical background,systematically studied in the present paper are the key techniques such as the type choice of the long-distance pipe-jacking machines applicable to rocky strata,lubricating to reduce the jacking resistance,long-distance guiding and rectification,the optimized provision of jacking relay stations and the like,all of which are already successfully applied to the actual construction of engineering projects and thus are of much value in popularizing their application.
作者 胡恒千 HU Hengqian(The Tunnel Engineering Co. Ltd.of the 18th Bureau Group of China Railway, Chongqing 400700, China)
出处 《国防交通工程与技术》 2020年第3期50-54,共5页 Traffic Engineering and Technology for National Defence
关键词 长距离 岩石顶管 设备选型 润滑减阻 导向与纠偏 中继间 long distance jacking pipes through the rocky stratum type-choice of equipment lubricate to reduce the jacking resistance guide and rectification jacking relay station
  • 相关文献

参考文献4

二级参考文献28

  • 1郝文峰.顶管工程设计中的顶力计算方法[J].甘肃科技纵横,2004,33(4):133-134. 被引量:6
  • 2马保松,张雅春.曲线顶管技术及顶进力分析计算[J].岩土工程技术,2006,20(5):229-232. 被引量:29
  • 3GB50268-2008给水排水管道工程施工及验收规范[S].
  • 4Jancsecz S, Steiner W. Face support for a large mix-shield in heterogeneous ground conditions[A]. Tunnelling 94, conference proeedings, Institution of Mining and Metallurgy and British Tunnelling Society[C]. London: Chapman and Hall, 1994. 531 -549.
  • 5Jefferis S A. Slurrids, Grouts. Chapter 48 of Construction Materials Reference Book[M]. Doran D K. Oxford:Butterworth- Heinemann, 1992.
  • 6Anagnostou, G. and Kovari, K. Face stability in slurry and EPB shield tunneling[J]. Tunnels and Tunnelling, 1996, 28(12): 27-29.
  • 7Milligan G W E, Norris P. Pipe-soil interaction during pipe jacking. Proceedings of the Institution of Civil Engineers[J]. Geotechnicai Engineering, 1999, 137(1): 27-44.
  • 8余彬泉 陈传灿.项管施工技术(第一版)[M].北京:人民交通出版社,1998..
  • 9马·谢尔勒.项管工程[M].北京:中国建筑工业出版社,1983..
  • 10候学渊 钱达仁 杨林德.软土工程施工新技术[M].合肥:安徽科学技术出版社,1999..

共引文献130

同被引文献35

引证文献7

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部