摘要
针对某轴承装配车间存在物流交叉和回流、资源配置不合理和生产线不平衡导致效率低下等问题,采用SLP和SHA工业工程的方法,分析现有装配车间的设施布局、物料搬运和物流通道,得出作业单位与物流关系和作业单位与非物流关系图。优化物流路线、物流通道和搬运设施类型及数量,分析对比了新旧方案的产能和平衡率,最后用3D Max软件绘制出轴承装配车间的三维效果图。实践表明,优化后生产效率大大提升。
Aiming at the problems of low efficiency in a bearing assembly workshop caused by logistics crossover and backflow,unreasonable resource allocation,and imbalanced production lines,the industrial engineering methods of SLP and SHA were utilized to analyze the existing assembly workshop layout,material handling and logistics channels.The relationship between operation unit and logistics,and operation unit and non-logistics were obtained.The logistics route,logistics channel,type and quantity of handling facilities were optimized.The capacity and balance rate of the old and new schemes were analyzed and compared,and the 3D rendering of the bearing assembly workshop was drawn with 3d Max.The practice shows that the optimized production efficiency is greatly improved.
作者
陈梦柯
黄浩浩
陈阳阳
王慧敏
王康
CHEN Mengke;HUANG Haohao;CHEN Yangyang;WANG Huimin;WANG Kang(School of Mechanical and Electrical Engineering,Lanzhou University of Technology,Lanzhou 730050,China)
出处
《机电工程技术》
2020年第2期45-49,共5页
Mechanical & Electrical Engineering Technology
关键词
轴承装配车间
布局
物流优化
仿真
bearing assembly workshop
layout
logistics optimization
simulation