摘要
无锡市惠山区前洲镇建设一座日处理量为150 t/d的垃圾转运站。本文介绍转运站配套渗滤液处理站的工艺设计,主要从设计水量、水质、工艺流程设计、各处理单元设计和投资与运行成本分析等方面进行叙述。可以为其他类似渗滤液处理设计提供参考。
A waste transfer station with treatment capacity of 150 tons per day was decided to be built in qian zhou town of hui shan district of Wuxi.This paper introduced the process design of the leachate treatment of the transfer station,which mainly included the water quantity of design,water quality of design,technological process of design,each processing unit,analysis of investment and operation cost.It provided reference for the design of other leachate treatment.
作者
陈秋萍
Chen Qiuping(Wuxi Municipal Design Institute Co.,Ltd.,Wuxi 214000,China)
出处
《广东化工》
CAS
2020年第9期152-153,共2页
Guangdong Chemical Industry