注浆加固技术在破碎顶板治理中的应用 被引量:4

Application of Grouting Reinforcement Technology in Broken Roof Treatment
下载PDF
导出
摘要 针对盛泰煤业15201综采工作面顶板破碎的问题,提出了提前预注浆加固顶板的控制技术,对钻孔过程中易发生卡钻的现象,采用了分段成孔工艺,保证了注浆顺利进行。现场应用结果表明,注浆后顶板最大下沉量降低了47.6%,超前支撑压力降低了18.6%,顶板稳定性及承载能力明显提高,注浆效果显著,为矿井安全生产创造了良好的条件。 Aiming at the problem of roof broken in 15201 fully mechanized coal mining face of Shengtai Coal Industry,this paper puts forward the control technology of reinforcing roof by pre-grouting in advance.The results of field application show that the maximum subsidence of roof is reduced by 47.6%,the pressure of leading support is reduced by 18.6%,the stability and bearing capacity of roof are improved obviously,the grouting effect is remarkable,and good conditions are created for mine safety production.
作者 朱少杰 ZHU Shao-jie(Shanxi Coal Marketing Group,Shengtai Coal Industry Co.,Ltd.,Gaoping 048400,China)
出处 《煤》 2020年第4期21-22,49,共3页 Coal
基金 内蒙古自然科学基金项目资助(2018LH05009)。
关键词 注浆加固 破碎顶板 钻孔 围岩稳定性 grouting reinforcement broken roof drilling stability of surrounding rock
  • 相关文献

参考文献5

二级参考文献33

共引文献24

同被引文献21

引证文献4

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部