摘要
针对工作面设备安装效率低等问题,马脊梁矿安装队通过技术研究,对8210综采工作面传统设备安装工艺进行了优化。实际应用表明:优化后工艺可缩短工作面设备安装周期达15 d,安装质量提高至95%以上,应用成效显著。
Aiming at the low installation efficiency of working face equipment, the installation team of Majiliang Mine optimizes the traditional installation technology of 8210 fully mechanized face through technical research. Actual application shows that the optimized process can shorten the installation period of working face equipment up to 15 d,and improve the installation quality to more than 95%.
作者
曹宇
Cao Yu(Majiliang Mine,Datong Shanxi 037027)
出处
《机械管理开发》
2020年第8期181-182,198,共3页
Mechanical Management and Development
关键词
技术设备
综采工作面
工艺优化
设备安装
technical equipment
fully mechanized mining face
process optimization
equipment installation