摘要
本文综合利用多种信息化技术进行高海拔藏区电网工程管控系统方案的设计,通过对工程建设业务管理需求的分析,整合移动应用、生物识别等技术手段开展建设过程中人员、风险、作业过程的业务管理,形成一套服务于工程管理的技术方案,为电网工程建设的信息化管理提供参考。
In this paper,a variety of information technology is used to design the management and control system scheme of power grid project in high altitude Tibetan area.Through the analysis of the business management requirements of engineering construction,the business management of personnel,risk and operation process in the construction process is carried out by integrating mobile application,biometric technology and other technical means,forming a set of technical scheme serving for project management,providing reference for information management of power grid engineering construction.
作者
边巴
尉涛
朱二雷
Penpa;YU Tao;ZHU Er-lei(State Grid Tibet Electric Power Co.,Ltd.,Lhasa 850000,China;Beijing North-Star Digital Remote Sensing Technology Co.,Ltd.,Beijing 100120,China)
出处
《价值工程》
2020年第26期215-216,共2页
Value Engineering
基金
国家电网有限公司科技项目资助(合同号:SGXZJG00JCJS1900028)。
关键词
电网工程
高海拔藏区
施工管控
power grid project
high altitude Tibetan area
construction control