期刊文献+

呼伦贝尔山金矿业极薄矿脉采矿工艺研究 被引量:3

Study on Mining Technology of Extra-Thin Vein of Shandong Gold Mining Industry in Hulunbuir
下载PDF
导出
摘要 呼伦贝尔山金矿业辖属三河矿区矿脉形态多变,岩体稳固性差,原有平底结构浅孔留矿法开采极薄矿体极易造成采场贫化率高、损失率大等问题。针对高品位急倾斜极薄矿体的开采特点,矿山决定变革采矿工艺采用电耙削壁充填法,结合钢筋混凝土人工假底替换矿房顶底柱,以此提高矿石回收率并降低生产成本,本设计可对具有类似条件的中小型矿山提供若干点借鉴意义。 Sanhe mining area,which belongs to Shandong Gold Mining Industry in HulunBuir,is characterized by variable vein shape and poor rock stability.The original shallow hole ore-retaining method with flat bottom structure can easily cause problems such as high dilution rate and high loss rate of stope.In view of the mining characteristics of high grade steeply inclined extremely thin ore body,the mine decided to change the mining technology and adopt the electric rake wall cutting filling method,combined with the artificial reinforced concrete bottom to replace the roof and bottom pillar of the mine,to improve the ore recovery and reduce the production cost.This design can provide some references for the small and medium-sized mines with similar conditions.
作者 李永新 赵兴东 王庆磊 黄雪松 LI Yong-xin;ZHAO Xing-dong;WANG Qing-lei;HUANG Xue-song(Hulunbuir Shandong Gold Mining Co.,Ltd.,Genhe 022357,China;Geomechanics Research Center,Northeastern University,Shenyang 110819,China)
出处 《有色矿冶》 2021年第3期19-22,共4页 Non-Ferrous Mining and Metallurgy
基金 NSFC—山东联合基金(U1806208) 中央高校基本科研业务费(N2001033)。
关键词 极薄矿脉 削壁充填法 人工假底 回采工艺 extra-thin vein waste-lifting filling method artificial false bottom mining method
  • 相关文献

参考文献8

二级参考文献33

共引文献28

同被引文献24

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部