摘要
跨越铁路是集电线路施工中的常见问题,跨越铁路对施工技术有着很高的要求。以华润山西中阳三期50 MW风电项目35 kV集电线路工程为例,介绍在地形复杂、严寒恶劣天气条件下跨越电气化铁路施工的关键环节,并提出相应施工技术难题的控制措施。
Crossing railway is a common problem in the construction of power collection line,and it has high requirements for construction technology.Taking the 35 kV power collection line project of Shanxi Zhongyang phase III 50 MW wind power project of China Resources as an example,the key links in the construction of crossing the electrified railway under the conditions of complex terrain and severe cold weather are introduced,and the control measures for the corresponding construction technical problems are put forward.
出处
《建筑技术开发》
2021年第10期33-34,共2页
Building Technology Development
关键词
集电线路
跨越铁路
施工技术
power collecting line
crossing railway
construction technology