摘要
同舟煤业露天矿为解决建设初期施工人员及机电设备不足的问题,采用土方剥离工程全外委的经营方式。结合同舟煤业的具体情况,分析了工程外委施工存在的七方面主要问题,针对这些问题,给出了露天煤矿外委施工安全管理的针对性措施,在实际应用的过程中具有良好的效果。
In order to solve the problem of shortage of construction personnel and mechanical and electrical equipment at the initial stage of construction,Tongzhou Coal Open-pit Mine adopts the management mode of the whole external committee of the earthwork stripping project.Combined with the specific situation of Tongzhou Coal Industry,this paper analyzes the seven main problems existing in the external construction of the project,and in view of these problems,puts forward the targeted measures for the safety management of the external construction of open-pit coal mine,which has a good effect in the process of practical application.
作者
张文建
Zhang Wenjian(Datong Coal Mine Group Xinzhou Tongzhou Coal Industry Co.,Ltd.,Shanxi Xinzhou 036600)
出处
《山东煤炭科技》
2021年第9期225-227,共3页
Shandong Coal Science and Technology
关键词
露天煤矿
外委工程
安全管理
open-pit coal mine
outsourced project
safety management