摘要
我国正处于调整能源结构的过程中,大力发展燃气-蒸汽联合循环技术。该技术大大提高了能源利用率,具有良好的社会效率、节能效益和环境效益。本文介绍了阿尔斯通KA13E2“一拖一”多轴抽凝背压联合循环机组主厂房布置的设计成果,并与“一拖一”双抽凝联合循环机组主厂房布置进行优化比选,为同类型工程的设计优化工作开拓了思路。
China is in the process of adjusting its energy structure,vigorously developing gas-steam combined cycle technology.This technology greatly improves energy utilization and has good social,energy-saving and environmental benefits.This article introduces the design results of the main plant layout of the Alstom KA13E2“one tow one”multi-shaft condensing back pressure combined cycle unit,and optimizes the layout of the main plant of the“one tow one”double condensing combined cycle unit.The design optimization work of the same type of project opened up ideas.
出处
《电力系统装备》
2021年第21期17-19,共3页
Electric Power System Equipment