基于关联图和层次分析法的特点,分析供电公司智能电能表检定过程时间长问题。利用关联图定性分析检定时间长的各项原因之间的关系,并采用层次分析法定量计算各原因对问题的影响程度。最后通过某电力公司的实际案例,证明提出的分析方法满足要求,同时根据分析出的问题研制了一种装置。
Based on the characteristics of correlation graph and analytic hierarchy process(AHP),this paper analyzes the problem of long verification time of smart watt hour meter in power supply company.The relationship between the causes of long verification time is analyzed qualitatively by using the correlation diagram,and the influence degree of each cause on the problem is calculated quantitatively by using the analytic hierarchy process.Finally,a practical case of a power company in Zhejiang province proves that the proposed analysis method meets the requirements,and a device is developed according to the problems.
作者
姜瑛
王艺轩
熊剑峰
朱东骏
汪如毅
JIANG Ying;WANG Yixuan;XIONG Jianfeng;ZHU Dongjun;WANG Ru-yi(Quzhou Guangming Electric Power Engineering Co.,Ltd,Zhejiang Quzhou 324002,China;State Grid Quzhou Power Supply Company,Zhejiang Quzhou 324002,China)
出处
《电工材料》
CAS
2022年第1期76-77,共2页
Electrical Engineering Materials
关键词
关联图
层次分析法
智能电能表
检定
correlation diagram
analytic hierarchy process
smart meter
verification