隧道中埋式止水带安装新工艺技术研究 被引量:6

Study on New Installation Technology of Buried Water Stop in Tunnel
下载PDF
导出
摘要 铁路隧道二衬施工时,因为施工工艺、材料等因素,导致中埋式止水带线形弯曲、埋设位置不精准、深浅不一等质量通病。哈牡客专玉白隧道施工中,纵向施工缝中埋式止水带借助纵向托夹“张拉式”安装新技术,另外环向施工缝通过T型定位筋准确定位,引入加劲型止水带,确保了中埋式止水带的位置的准确性、平顺度和深度,提高了防水效果和施工工效,节约了成本。 During the construction of secondary lining of railway tunnel,due to construction technology,materials and other factors,the project is prone to some common quality problems such as linear bending,inaccurate embedding position and different depth of buried-in-middle water stop.In the construction of Yubai tunnel of Harbin-Mudanjiang passenger dedicated line,the embedded water stop in the longitudinal construction joint is installed with the help of the new technology of“tensile style”installation of longitudinal supporting clip.In addition,the circumferential construction joint is accurately positioned through T-shaped positioning bar,and stiffened water stop is introduced,which ensures the accuracy,smoothness and depth of the position of the buried water stop,improves the waterproofing effect and construction efficiency,and saves the cost.
作者 万军 Wan Jun(The Fourth Engineering Co.,Ltd.of China Railway 18th Bureau Group,Tianjin300350,China)
出处 《中国建筑防水》 2022年第6期51-55,共5页 China Building Waterproofing
关键词 铁路隧道 中埋式止水带 张拉式安装 加劲型止水带 T型定位筋 railway tunnel buried water stop tensile installation stiffening water stop T-shaped positioning bar
  • 相关文献

参考文献5

二级参考文献23

共引文献10

同被引文献30

引证文献6

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部