针对电厂整个燃煤输送系统设计及运行中存在的煤尘污染问题,设计提出防偏导密闭料槽及水雾联合除尘系统,并进行了应用。结果表明,采用以上除尘系统,既可减少投资,又能降低运行成本,并且能够大幅降低粉尘造成的污染,其减排、节能的效果显著。
In view of the coal dust pollution problems in the design and operation of the whole coal conveying system of the power plant,an anti-deflection closed chute and water mist combined dust removal system was designed and applied.The results show that the above dust removal system can reduce both investment and operation cost,and can significantly reduce the pollution caused by dust,and its effect of emission reduction and energy saving is remarkable.