摘要 基于武汉嘉里汉正街B1地块基坑工程,指出长江一级阶地滨江基坑工程应根据场地实际、长江水位历史变化、场区历史最低承压水水位、周边已完工项目影响、施工时间节点等因素综合评估降水引起的地面沉降影响,进而选择合适止水帷幕选型;电梯井坑中坑的优化设计与支护桩与止水帷幕同轴共中心线施工的方案,进一步解决了工程降本增效的经济要求。项目的实施为武汉都市发展区长江一级阶地沉降严控区基坑工程提供了参考。 Based on the foundation pit project of the Jiali B1 plot of Hanzheng Street,Wuhan,it is summarized that the foundation excavations of the first terrace of the Yangtze River should comprehensively evaluate the impact of ground settlement caused by precipitation based on factors such as actual site conditions,historical changes in the Yangtze River water level,the historical lowest confined water level in the site area,the impact of completed projects in the surrounding area,and construction time nodes,and then select appropriate curtain for cutting off drains.The optimized design of the pit in the elevator shaft and the coaxial and collinear construction plan of the support pile and curtain for cutting off drains further solve the economic requirements of cost reduction and efficiency increase in the project.The implementation of the project provides a reference for the foundation pit engineering of the Yangtze River first terrace settlement strict control area in Wuhan Urban Development Zone.
作者 权威 朱浦栋 谷喜权 Quan Wei;Zhu Pudong;Gu Xiquan(Central South Exploration&Foundation Engineering Co.,Ltd.,Wuhan Hubei 430082,China;Wuhan Lutong Municipal Engineering Quality Testing Center Co.,Ltd.,Wuhan Hubei 430010,China)
出处 《山西建筑》 2023年第19期62-65,共4页 Shanxi Architecture
关键词 一级阶地 基坑 止水帷幕 坑中坑 同轴施工 first terrace excavations unclosed curtain for cutting off drains pits in foundation-pit coaxial construction
  • 相关文献

参考文献7

二级参考文献37

共引文献101

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部