摘要 为了满足石头梅露天煤矿爆破和剥采工程计量的需求,基于对3DMine矿业软件功能的研究与应用,探讨了爆破和剥采工程分水平计量,并进行了剥采工程运距及提升高度计算。结果表明:利用3DMine矿业软件计算工程量速度快、精度高,同时解决了石头梅露天煤矿爆破和剥采工程分水平计量、剥采工程运距和提升高度计算难的问题,提高了工程量验收工作的效率及质量。 In order to meet the demand of blasting and stripping engineering measurement in Shitoumei Open-pit Coal Mine,based on the research and application of 3DMine mining software functions,this article discusses the horizontal measurement of blasting and stripping engineering,and the calculation of stripping engineering haul distance and lifting height.The results show that the 3DMine mining software is fast and accurate in calculating the quantities,and solves the problems of horizontal measurement of blasting and stripping engineering,calculation of stripping engineering haul distance and lifting height in Shitoumei Open-pit Coal Mine,and improves the efficiency and quality of engineering quantity acceptance.
作者 刘兴学 LIU Xingxue(Hami Branch of Xinjiang Energy(Group)Co.,Ltd.,Hami 839000,China)
出处 《露天采矿技术》 CAS 2023年第5期55-57,61,共4页 Opencast Mining Technology
关键词 3DMine 三角网法 分水平计量 运距 提升高度 3DMine triangular network method level measurement haul distance lifting height
  • 相关文献

参考文献9

二级参考文献37

共引文献27

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部