切眼扩刷无锚支护一体化施工工艺应用 被引量:1

Application of the Integrated Construction Technology of Cut and BrushingBolt-free Support
下载PDF
导出
摘要 为工作面快速具备采煤条件,解决工作面切眼扩刷与支架安装时间周期长、工艺复杂的问题,提出无锚支护一体化施工工艺,经过工艺改进,利用单体柱代替锚网索加固扩帮段巷道顶板,后巷紧跟液压支架安装的平行作业方式,经实践表明:切眼扩刷无锚支护一体化施工较扩帮锚网索支护工艺节约18天工期,节约生产成本14.2万元。 In order to quickly meet the mining conditions of the working face and solve the problems of long time cycle and complex process of cutting hole expansion and bracket installation,the paper proposes an integrated construction process without anchor support,using a single column to replace the anchor mesh cable to reinforce the roof of the expanded section of the roadway,and the rear roadway following the parallel operation method of hydraulic support installation,whose practice has shown that the integrated construction of cutting,expanding,brushing,and anchor free support saves 18 days of construction time and 142000 yuan in production cost compared to the expansion of anchor net and cable support process.
作者 郭磊磊 Guo Leilei(Bofang Colliery Branch,Shanxi Lanhua Science and Technology Venture Co.,Ltd.,Gaoping,Shanxi 048400)
出处 《江西煤炭科技》 2023年第4期26-28,32,共4页 Jiangxi Coal Science & Technology
关键词 工作面切眼 无锚支护技术 扩帮 支架安装 平行作业 coal mining face open-off cut no bolt supporting technology side slope extension support installing parallel operation
  • 相关文献

参考文献5

二级参考文献35

共引文献12

同被引文献7

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部