韶钢8号高炉计划检修延时复风操作实践

Practice of Delayed Air Resumption Operation in Scheduled Maintenance of No.8 Blast Furnace at Shaogang
下载PDF
导出
摘要 韶钢8号3 200 m^(3)高炉计划定修28 h,主控项目更换4号热风阀,受拆除热风阀法兰处耐衬的影响,热风阀拆除难度较大,导致高炉延迟复风18 h,针对此制订了详细的复风方案,通过精心组织高炉操作,确保了复风的整体顺利进行,也验证了韶钢炼铁厂针对异常情况的快速应对能力,杜绝了工艺事故的发生,实现了炉况快速安全恢复。 The No.83200 m^(3) blast furnace of SISG is scheduled to be repaired for 28 hours,and the main control project is to replace the No.4 hot air valve.Due to the influence of the removal of the hot blast valve flange lining,the removal of hot blast valve is difficult,resulting in the delay of the blast furnace re blowing for 18 hours.A detailed re-blowing scheme is formulated,and the blast furnace operation is carefully organized to ensure the overall smooth re blowing,which also verifies the rapid response ability of SISG iron making to abnormal conditions.The process accident is eliminated and the furnace condition is restored quickly and safely.
作者 林贤文 毛佳 詹开洪 Lin Xianwen;Mao Jia;Zhan Kaihong(Iron Making Plant,Guangdong Shaoguan Iron and Steel Co.,Ltd.,Shaoguan Guangdong 512123,China)
出处 《山西冶金》 CAS 2024年第1期148-150,共3页 Shanxi Metallurgy
关键词 高炉 延迟复风 安全 恢复炉况 blast furnace delay the resumption of wind safety restore furnace condition
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部