摘要
BIM技术应用于桥梁现浇箱梁施工中,用精细化管理模式来代替传统的粗放型管理模式,可明显提高施工质量。论文以四川省内江市水心坝大桥为例,深入探讨了BIM技术在桥梁现浇箱梁施工中的应用,包括三维施工场地布置、支撑体系设计、碰撞协调优化、工程量统计、施工进度模拟、施工进度管理等,有效地确保了该项目保质保量地完成。
When BIM technology is applied to the construction of cast-in-place box girders of bridges,it can replace the traditional extensive management mode with the refined management mode,which can significantly improve the construction quality.Taking Shuixinba Bridge in Neijiang City,Sichuan Province as an example,the application of BIM technology in the construction of cast-in-situ box girders of bridges is deeply discussed,including three-dimensional construction site layout,support system design,collision coordination optimization,quantity statistics,construction schedule simulation,construction schedule management,etc.,which effectively ensures the completion of the project with quality and quantity guaranteed.
作者
王燕
金鹂娜
WANG Yan;JIN Li-na(Changxing County Transportation Survey and Design Institute Co.Ltd.,Changxing 313100,China;Changxing Transportation Management Consulting Co.Ltd.,Changxing 313100,China)
出处
《工程建设与设计》
2024年第5期180-182,共3页
Construction & Design for Engineering
关键词
BIM技术
桥梁
现浇箱梁
施工
BIM technology
bridge
cast-in-situ box girder
construction