期刊文献+

回采巷道锚注加固超前支护技术研究

Advance Support Technology of Anchorage Injection Reinforcement in Mining Roadway
下载PDF
导出
摘要 针对永定庄矿复杂地质条件下回采巷道超前支护效率低的问题,以该矿8203工作面为工程背景,设计采用注浆锚索代替液压支柱的支护方案,通过数值模拟对不同锚索预紧力及间排距下的巷道垂直应力进行分析,从而得出最佳的锚索预紧力为150 k N,最佳间排距为1 800 mm×900 mm。通过现场应用,发现注浆锚索支护受力最大值小于100 kN,处于安全合理范围内,因此锚注加固超前支护方案可行,可以为地质条件类似的巷道支护提供参考。 Aiming at the low support efficiency of mining roadway under complex geological conditions in Yongdingzhuang Coal Mine,taking 8203 working face of the mine as the engineering background,a support scheme using grouting anchor cable instead of hydraulic prop was designed,and the vertical stress of roadway under different pretightening force and row spacing of anchor cable was analyzed by numerical simulation.Thus,the optimum cable pretightening force of 150 kN and the optimum row spacing of 1800 mm×900 mm were given.Through the field application,it was found that the maximum force of the grouting anchor cable support was less than 100 kN,which was within the safe and reasonable range.Therefore,the advance support scheme of anchorage injection reinforcement is feasible and can provide reference for the support of roadways under similar geological conditions.
作者 刘凯峰 LIU Kaifeng(Yongdingzhuang Coal Industry Company,Jinneng Holding Coal Industry Group,Datong 037024,Shanxi,China)
出处 《能源与节能》 2024年第4期215-218,共4页 Energy and Energy Conservation
关键词 高应力 回采巷道 联合支护 数值模拟 high stress mining roadway combined support numerical simulation
  • 相关文献

参考文献5

二级参考文献47

共引文献155

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部