摘要
为评价广州市南沙区某码头工程防洪安全,采用MIKE21水动力模型模拟200年一遇洪水条件下工程建设前、后水位、流速和流向等水力要素的变化,模型计算分析得出:工程建设后,水位壅高最大值不超过0.007 m,流速减小不超过0.39 m/s,流向偏转最大不超过13°。研究结果表明该码头工程的建设对所在河段的防洪和河势不会产生明显不利影响。
To evaluate the flood control safety of a dock project in Nansha District,Guangzhou,this paper uses MIKE21 hydrodynamic model to simulate the changes in hydraulic elements such as water level,flow velocity,and flow direction before and after the construction of the project under the condition of a 200 year flood.The model calculation analysis shows that after the construction of the project,the maximum water level rise does not exceed 0.007m,the flow velocity decreases by no more than 0.39m/s,and the maximum flow direction deviation does not exceed 13°.The research results indicate that the construction of the dock project will not have a significant adverse impact on the flood control and river regime of the river section where it is located.
作者
黄朝梅
刀海娅
孙岩
HUANG Chaomei;DAO Haiya;SUN Yan(Yunnan Institute of Water&Hydropower Engineering Investigation,Design and Research,Kunming 650000,China;Yunnan University,Kunming 650000,China)
出处
《云南水力发电》
2024年第7期166-170,共5页
Yunnan Water Power
基金
江苏省双创人才计划项目(2016A400)。
关键词
码头工程
MIKE21
防洪评价
水位
流速
流向
wharf engineering
MIKE21
flood control evaluation
water level
flow rate
flow direction