摘要 叶巴滩水电站地处青藏高原与川西北高原交接处,其地势高亢,气候寒冷且干燥,多大风且日照时间长,具有长冬无夏、短春秋的特点,属于国内外较为典型的高寒高海拔超长低温期大型水力发电工程。阐述了通过采取全天候连续施工、薄层短间歇施工、气肋膜三种施工技术,实现了大坝混凝土连续、高效、高质量的浇筑施工过程,混凝土外观检查未发现裂缝,温度指标满足设计要求。 The Yebatan Hydropower Project is located at the junction of the Qinghai Tibet Plateau and the Northwest Sichuan Plateau,with high terrain,cold and dry climate,frequent winds,and long sunshine.It has the characteristics of long winter,no summer,and short spring and autumn.It is a typical large-scale water conservancy and power generation project at high cold,high altitude,and ultra-long and low temperature periods both domestically and internationally.By adopting three construction methods:continuous construction throughout the day,thin-layer short-interval construction,and air-ribbed membrane construction,the dam concrete has been continuously,efficiently,and has effectively constructed high quality pouring construction,no cracks found during concrete appearance inspection,and temperature indicators meet design requirements.
作者 丁钇 欧作飞 张文博 DING Yi;OU Zuofei;ZHANG Wenbo(Sinohydro Bureau 7 Co.,Ltd.,Chengdu Sichuan 610213)
出处 《四川水力发电》 2024年第5期107-109,112,共4页 Sichuan Hydropower
关键词 叶巴滩水电站 高寒高海拔 薄层短间歇 气肋膜 Yebatan Hydropower Project High cold and high altitude Thin-layer short-interval Air-ribbed membrane
  • 相关文献

参考文献5

二级参考文献14

共引文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部