摘要
生产矿山的配矿环节受多种条件的制约,作者在考虑各种配矿受限条件的基础上,用混合型整数线性目标规划方法研究了用于露天矿和地下矿编制短期生产配矿计划的数学模型,并论述了数学模型的解算方法。
Ore blending in active mines is subject to numerous restrictions. The author, based on analysis on the various restrictions to ore blending, has established a mathematical model for planning short-term production ore blending for both open pit and underground mines, using the mixed integer linear target planning method. This paper discusses the solutions to the mathematical model.
出处
《矿业研究与开发》
CAS
2002年第6期1-3,59,共4页
Mining Research and Development
关键词
生产配矿计划
线性目标规划
约束条件
配矿数模
Plan of production ore blending, Linear target planning, Confinement, Mathematical model for ore blending