摘要 天然高陡坡地场地条件复杂,开挖平整场地困难且花费成本昂贵,可以考虑直接在原始高陡坡地上建造房屋,需要研究基础的有效嵌固,保证在高陡坡地上基础承载力、刚度以及充分的抗震性能。本文对某高陡坡掉层结构基础嵌固层的有效性进行了研究,提出解决高陡坡掉层结构无法有效嵌固的箱桩复合基础设计方案。通过计算基础在大震作用下水平承载力,以及分析结构掉层部分在大震下动力弹塑性的性能,验证了高陡坡下人为构造基础嵌固层是有效和可行的。 The natural high gradient site conditions are complex,and the excavation and leveling of the site is difficult and expensive.It can be considered to directly build houses on the original high gradient.It is necessary to study the effective embedding and fixation of the foundation to ensure the bearing capacity,stiffness and sufficient seismic performance of the foundation on the high gradient.In this paper,the effectiveness of the basic embedded layer about a high-slip slope structure is studied.A box-pillar composite foundation design scheme is proposed to solve the problem that the high-and-steep slope layer structure could not be effectively embedded.By calculating the horizontal bearing capacity under the action of large earthquakes and analyzing the performance of the dynamic elasto-plasticity of the strata of the structures under large earthquakes,it is verified that the artificial embedded foundation under large and steep slopes is effective and feasible.
作者 何云 李轩直 He Yun;Li Xuanzhi(CCTEG Chongqing Engineering Co.Ltd,Chongqing400016,China;Xingtai Polytechnic College,Xingtai054035,China)
出处 《建筑科学》 CSCD 北大核心 2019年第9期19-25,共7页 Building Science
关键词 高陡坡 掉层结构 嵌固层 箱桩基础 high steep slop structure supported by foundations with different elevations anchoring layer box and pile foundation
  • 相关文献

参考文献3

二级参考文献23

  • 1李宏男,赵衍刚.日本新潟县中越大地震震害调查及分析[J].自然灾害学报,2005,14(1):165-174. 被引量:17
  • 2刘金砺,祝经成.泥浆护壁灌注桩后注浆技术及其应用[J].建筑科学,1996,12(2):13-18. 被引量:81
  • 3蔡之瑞,孙柏涛.唐山地震震害与重建唐山[J].世界地震工程,1996,12(4):48-50. 被引量:3
  • 4戴志中.现代山地建筑接地诠释[J].城市建筑,2006,3(8):20-24. 被引量:42
  • 5中华人民共和国建设部主编.建筑抗震设计规范(GB50011-2001)[S].北京:中国建筑工业出版社,2001..
  • 6T Kabeyaswa,H Shioara and S Otani.U.S. Japan Cooperative Research on R/C Full-Scale Building Test-Part 5,Discussion on Dynamic Response System[A].Proc Of 8th WCEE[C].Vol.6,1984.
  • 7Federal Emergency Management Agency, NEHRP Guidelines for the Seismic Rehabilitation of Buildings[S]. FEMA273, Chapter 3,11 - 15, 1997.
  • 8Ghobrah A,Abou-Elfath H,Biddah A. Response-based Damage Assessment of Structures[J].Earthquake Engineering and Dynamics, 1999,28:79-104.
  • 9Krawinkler H, Pros and Cons of a Pushover Analysis of Seismic Performance Evaluation[J].Journal of Engineering Structures, 1998, 452-464.
  • 10清华大学土木工程结构专家组,西南交通大学土木工程结构专家组,北京交通大学土木工程结构专家组,叶列平,陆新征.汶川地震建筑震害分析[J].建筑结构学报,2008,29(4):1-9. 被引量:474