介绍了采用定向倒塌和折叠爆破拆除 4 3 5m高厂房的方案 ,并对爆破振动进行监测和分析 。
The demolition of a 43.5 m high workshop by directional collapsing and folding blasting is introduced.Blasting vibration has been monitored and analyzed. The blasting has reached an anticipative effect ,which can be used as a reference for similar projects.
出处
《爆破》
CSCD
2003年第1期39-42,共4页
Blasting
关键词
厂房
折叠爆破
拆除爆破
振动监测
workshop
folds blasting
demolition blasting
vibration monitor