地面多分支水平钻井与井下钻孔对接预抽瓦斯技术 被引量:8

Gas Pre-Drainage Technology of Ground Multi-Branch Horizontal Well Connected with Underground Mine Borehole
下载PDF
导出
摘要 针对现有的地面水平定向钻井开采煤层气及煤矿井下钻孔预抽煤层瓦斯受时间和空间限制的问题,提出了地面多分支水平钻井和井下钻孔对接预抽瓦斯技术,并在沙曲煤矿24307工作面对多分支水平钻井对接井下钻孔进行应用研究,对接后,瓦斯抽采钻孔XC01的产气量达6 000~7 000m2/d,瓦斯体积分数达95%;XC02的产气量基本稳定在12 000 m3/d左右,平均瓦斯体积分数达到了91.05%;大幅提高了单井产气量和瓦斯抽采效率。 According to the problem of time and space limitations when gas pre-drainage through underground mine borehole and ground multi-branch horizontal well,the gas pre-drainage technology of ground multi-branch horizontal well connected with underground mine borehole was put forward,and it was used in multi-branch horizontal connection well engineering of No. 24307 working face Shaqu Mine. After connection,the gas production rate of gas drainage borehole XC01 was 6 000~7 000 m3/d and the average gas concentration was 95%;the gas production rate of gas drainage borehole XC02 was around 12 000 m3/d and the average gas concentration was 91. 05%.The gas production of single well and gas drainage ratio grew significantly.
出处 《煤炭科学技术》 CAS 北大核心 2014年第5期48-50,54,共4页 Coal Science and Technology
基金 国家自然科学基金资助项目(51174198) 煤炭资源与安全开采国家重点实验室自主课题资助项目(SKLCRSM11X01)
关键词 地面多分支水平钻井 羽状井 井下钻孔 瓦斯预抽 ground multi-branch horizontal well pinnate well underground mine borehole gas pre-drainage
  • 相关文献

参考文献10

二级参考文献65

共引文献247

同被引文献124

引证文献8

二级引证文献104

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部