摘要
介绍了华能南京电厂 32 0MW机组汽轮机控制系统 (DEH)改造的基本情况 ,并结合工程实践对该系统在改造中应用的新技术和特点进行分析和评价。DEH改造后已稳定运行 1年 ,完全能满足对汽轮机安全、可靠。
The basic situation of the retrofitted steam turbine control system (DEH) for a 320 MW unit at Huaneng Nanjing Power Plant has been presented, and combined with engineering practice, the new techniques used in retrofitting the said system and their features have been analysed and evaluated. After retrofitting, the unit has stable operation for one year, completely satifying the requirments for stability, reliability and quick response in operation of steam turbines.
出处
《热力发电》
CAS
北大核心
2003年第6期57-59,63,共4页
Thermal Power Generation