摘要
齐大山铁矿矿石半移动破碎站的 3个组件组成和移设过程 ,为金属露天矿的间断 -连续运输工艺新技术的采用和新设备的利用提供了借鉴意见 ,以期获得最佳的经济效果。
The experience of assembly(3 components)and shift of semi-mobile crushing plant in Qidashan Iron Ore Mine can be taken for reference in the case that new technology and new equipment of intermittent-continuous haulage system are adopted for achieving high economic profits.
出处
《矿业工程》
CAS
2003年第4期45-49,共5页
Mining Engineering