摘要
在前期施工过程中,该50m砖烟囱垂直运输设备出现了严重的安全事故,特对烟囱的施工技术措施进行了详细的研究,在详细计算分析的基础上,重点对脚手架、垂直运输和人行通道进行了重新设计,保证了后期施工的顺利完成。
In the prophase construction of the 50m brick chimney,serious problems happened in the vertical transportation equipment,so detail research has been made on the construction technology of chimney.Based on the detail calculation and analysis,the scaffold,vertical transportation equipment and pedestrian passage were redesigned to guarantee the smooth accomplishment of the upper construction.
出处
《施工技术》
CAS
北大核心
2011年第S2期152-155,共4页
Construction Technology
关键词
砖烟囱
施工技术
垂直运输
brick chimney
construction technology
vertical transportation