摘要
桥梁工程的支座是连接桥梁上部和下部结构之间的构件,有承上启下的作用,使用过程受荷载因素和自然因素的作用,容易出现病害,影响桥梁的正常使用。着重介绍支座更换施工方案、方法及技术措施、合理化建议,结合实际施工案例,演绎详细施工计算,对类似工程的施工具有一定的借鉴意义。
The bearing of bridge engineering is the bridge between the upper and lower member connection structure,a connecting role,using load factors and natural factors,prone to disease,affect the normal use of the bridge. This paper emphatically introduces the construction scheme,method and technical measures of support replacement,reasonable suggestion,combined with the actual construction case,deduction of detailed construction calculation,which has certain reference significance for the construction of similar projects.
出处
《施工技术》
CAS
北大核心
2017年第S1期951-954,共4页
Construction Technology
关键词
桥梁工程
支座更换
施工
bridge engineering
bearing replacement
construction