极硬岩地层地下连续墙双轮铣快速成槽技术 被引量:8

Rapid Trenching Technology of Double Wheel Trench in the Extremely Hard Rock Underground Diaphragm Wall
下载PDF
导出
摘要 以广州地铁18,22号线番禺广场地铁站项目为依托,针对双轮铣在极硬岩地层条件下成槽进尺慢的现状,采用不同施工工法。实践表明重锤配合双轮铣施工工法能明显提高成槽效率:设备的检修次数减少;更换钻齿的次数和数量明显减少;更换钻齿次数约为不用重锤工况的1/2,更换钻齿的数量为1/10;成槽时间明显降低;中风化花岗岩中的钻进效率提高2倍左右;微风化花岗岩中的钻进效率提高4~6倍。 This paper is based on the project of Panyu Square interchange station for line 18 and 22 of Guangzhou Metro,aims at the current construction situation that the slow grooving progress of using hydraulic double wheel trench cutter under the extremely hard rock formation condition,the different construction method is applied.The study indicates that the construction method which using heavy punch with hydraulic double wheel trench cutter can distinctly improve the efficiency of grooving:The frequency of machine maintenance is reduced.The frequency and quantity of changing drilling teeth are significantly reduced.The frequency of changing drilling teeth is about half of which construction without using heavy punch,and the quantity of changing drilling teeth reduces to 1/10.The grooving period is distinctly shorter.The drilling efficiency in the intermediary weathered granite is improved about 2 times.The drilling efficiency in the breeze granites is improved 4~6 times.
作者 李有道 许丹 王强 阳书燕 LI Youdao;XU Dan;WANG Qiang;YANG Shuyan(China Railway 11th Bureau Group Co.,Ltd.,Wuhan,Hubei 430061,China;China Railway 11th Bureau Group Fourth Engineering Co.,Ltd.,Wuhan,Hubei 100855,China)
出处 《施工技术》 CAS 2018年第A04期1463-1465,共3页 Construction Technology
关键词 地铁车站 极硬岩 地下连续墙 双轮铣 成槽 subway station extremely hard rock underground diaphragm wall double wheel trench trench
  • 相关文献

参考文献5

二级参考文献11

共引文献29

同被引文献53

引证文献8

二级引证文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部