摘要
介绍了厦门枢纽既有概况,分析了近远期的厦门枢纽客车车流特点,对厦门枢纽内客运站厦门站、厦门北站、漳州北站、漳州站的现状进行了研究。结合厦门市和漳州市城市总体规划和综合交通规划,对福厦客专如何引入厦门枢纽的客运系统研究了若干方案,通过对各个方案优缺点深入分析,得出了福厦客专引入厦门枢纽的推荐方案,即在不进岛设站,沿既有通道接入漳州北站,联络线引入厦门北站、角美站方案。
This paper introduces the existing situation of Xiamen hub,analyzes the passenger traffic characteristics of Xia-men hub in the short and long term,also studies the status of Xiamen Railway Station,Xiamen North Railway Station,Zhan-gzhou North Railway Station,Zhangzhou Railway Station within Xiamen hub.Combined with the general urban planning and comprehensive transportation planning,this paper studies several schemes for Fuzhou to Xiamen passenger dedicated line on how to introducing into the passenger system of Xiamen hub,through in-depth analysis on the advantages and disadvantages of each scheme,it comes to the best scheme that is,station is set outside the Xiamen Island,Zhangzhou North Railway Station is connected to along the existing line,link line is joined into Xiamen North Railway Station,Jiaomei Railway Station.
出处
《铁道建筑技术》
2015年第6期57-62,共6页
Railway Construction Technology
关键词
福厦客专
厦门枢纽
客运系统
方案研究
Fuzhou to Xiamen passenger dedicated line
Xiamen hub
passenger system
scheme research